- Redundancy (as published)
- Building incoming power equipment: 2-feeder wiring / generator configuration N + 1 / UPS configuration N + 1 / air-conditioner configuration N + 2 (telehouse.com/ja); incoming power method 77kV main and standby line method / in-house generators N+1 redundant configuration (48 hours or more of operation without refuelling) / UPS equipment N+1 redundant configuration (15 minutes of supply) / air-conditioner configuration N+2 redundant, with UPS (KDDI 2015-08-20)
- Security
- 24/7 on-site security
- Year built
- 2015
- Rack density
- 18 kW
Platform reviewed · 26 Sept 2026 · Recent
- Density (as published)
- Power/rack: max. effective 20kVA, average effective 10kVA (telehouse.com/ja); max. rated 30kVA (effective 20kVA) per rack; average rated 15kVA (effective 10kVA) per rack (KDDI 2015-08-20)
- Power band
- 5–20 MW
Platform reviewed · 26 Sept 2026 · Recent
- Cooling
- Air cooling
- Availability
- Availability on request
Imported · Recorded 08 Jun 2026 · Not recent
- Cross-connect
- On request
- Design PUE
- Design PUE 1.2 to 1.4
- PUE note
- Design PUE of 1.37.
- Services
- Colocation, connectivity and high-density
- Certifications 1
- ISO 27001
Interested in this location? Send one inquiry with your requirements and receive a response within one business day.
Data sources
This profile is based on public sources; the operator has not yet confirmed its data. Confirmed data carries the Verified badge and a confirmation date.
Do you manage this datacenter? Claim your listing at no cost and keep the data current yourself.