- Redundancy (as published)
- Mita campus: the underground power cables are fully duplicated in 2 circuits, allowing equipment maintenance and renewal without outage. Incoming power uses the main and standby line method, with no outage during maintenance. · UPS uses a block redundant method with a further N+1 as common standby for each N+1 UPS set. · Gas-turbine generators installed in N+1 configuration; 72 hours of continuous operation without refuelling possible. · Air conditioners also have dual power inputs, allowing continued operation through circuit switching during inspections. | SH1/SH2: UPS block redundant method (10-minute cover) · water-cooled central air conditioning (N+2 redundant configuration) (specification table Mita campus, 26-09-2026)
- Security
- 24/7 on-site security
- Density (as published)
- SH2: power per rack (standard) effective 4kVA, (max.) effective 8kVA (press release 03-09-2018; brochure SH2 July 2018) | high-load housing service, offered at the Inzai campus and the Mita campus: rack power 30kVA or more, depending on customer requirements and the combination of cooling methods (brochure high-load housing service, as of April 2024)
- Cooling
- Air cooling, Direct-to-chip, Rear-door heat exchanger
- Availability
- Availability on request
Imported · Recorded 08 Jun 2026 · Not recent
- Cross-connect
- On request
- PUE note
- Target PUE of 1.3; not a measured figure.
- Services
- Colocation and high-density
- Certifications 1
- PCI DSS
Location
View on the full map · Elevation 250 m above sea level

Interested in this location? Send one inquiry with your requirements and receive a response within one business day.