- Site status
- Under construction
- Expected operational
- Q3 2026
- Design resilience tier
- III
- Redundancy (as published)
- "Tier IV resilience for PFE hosting, Tier III+ for all Interconnection and IT workloads" (GEN01); "Minimum redundancy of N+2 cooling to data halls"; "N+1 Distributed Redundant topology"; "Every rack gets a true N+N power connection"
- Floor area
- 9,000 m² total building
- Rack density
- 6 kW
Platform reviewed · 25 Sept 2026 · Recent
- Power band
- 5–20 MW
Platform reviewed · 25 Sept 2026 · Recent
- Availability
- Availability on request
Imported · Recorded 08 Jun 2026 · Not recent
- Cross-connect
- On request
- PUE note
- Operator-wide claim: target PUE below 1.25.
- Services
- Colocation and connectivity
Location
View on the full map · Elevation 39 m above sea level

Interested in this location? Send one inquiry with your requirements and receive a response within one business day.
Data sources
This profile is based on public sources; the operator has not yet confirmed its data. Confirmed data carries the Verified badge and a confirmation date.
Do you manage this datacenter? Claim your listing at no cost and keep the data current yourself.